Roadway News & More
9/15/2023 Wegmans Update We plan to turn the space over to Wegmans in early Spring of 2024, after which they will begin to build out the...


The Brick Goes On And On And On
6/06/2023 Brick Work Is Well Underway! As we progress with the brick façades around all sides of the new building, a variety of building...


And The Brick Goes On
5/10/2023 Brick Laying Has Begun! You will notice two different colors of brick along the side of the building that faces the future...


Façade Layering Has Begun
3/28/2023 Good news! We have started work on the building façade. Constructing the façade is done in layers, starting with steel...


Twinbrook Quarter Is Shaping Up
1/27/2023 January brings steady progress at the site. Concrete pours have been completed through the ninth floor and we’re in the process...


Twinbrook Quarter in the Community
Twinbrook Quarter Goes Purple! In support of “Rockville Goes Purple,” we installed an array of purple lighting on the three cranes at the...


Completing Concrete Pouring Level 3
10/25/2022 Level 3 concrete pouring is nearly complete and we will continue pouring concrete for Level 4. Levels 1-4 contain Wegmans, the...

Second Level Concrete Pouring Underway
9/6/2022 We are approximately one-third finished pouring the second level slab for Phase One. We expect to be 60% finished with the...
Interesting Photos from Construction Site
8/15/22 A recent Rockville Nights blog shared some interesting photos from our construction site. You can see them here.


We're Going Above Ground!
7/6/22 Almost at Halfway Mark for Ground Level Slab Within the next two weeks, we hope to be almost 50% finished pouring ground level...